Street lamp light covered

Adroddwyd drwy mobile yn y categori Light blocked by vegetation yn ddienw am 00:17, Iau 26 Mehefin 2025 using FixMyStreet Pro

Anfon at Bromley Council llai na munud yn hwyrach. Cyfeirnod FixMyStreet: 7765318.

The public footpath/alleyway from Eton Road to Arundel Drive in the BR6 area is not lit up enough due to the heavy ivy growth hanging over the street lamp. The street lamp is located in the alleyway on the border of the playing field of The Highways School. This has been reported before but it hasn’t been attended to. Thankyou for your attention to this issue

Asset ID: 48-F-1

Diweddariadau

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    Cyflwr wedi newid i: In progress

    Postiwyd gan Bromley Council am 00:18, Iau 26 Mehefin 2025

  • Our contractor has been notified to take the appropriate action.

    Postiwyd gan Bromley Council am 07:55, Mer 2 Gorffennaf 2025

  • Appropriate action has been taken to resolve the issue.

    Cyflwr wedi newid i: Fixed

    Postiwyd gan Bromley Council am 15:09, Mer 9 Gorffennaf 2025

  • I walked through the alleyway today 10th July and I can report that the work is still outstanding. Ivy is still present, no works have been carried out

    Cyflwr wedi newid i: Agor

    Postiwyd yn ddienw am 11:42, Iau 10 Gorffennaf 2025

  • Further works are necessary to resolve the issue and have been scheduled for action.

    Cyflwr wedi newid i: In progress

    Postiwyd gan Bromley Council am 08:25, Gwen 11 Gorffennaf 2025

  • We are continuing to investigate and working to resolve this report

    Postiwyd gan Bromley Council am 08:44, Gwen 11 Gorffennaf 2025

  • Your report is being investigated further. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    Postiwyd gan Bromley Council am 15:28, Gwen 11 Gorffennaf 2025

  • Our contractor has been notified to take the appropriate action.

    Postiwyd gan Bromley Council am 14:16, Mer 16 Gorffennaf 2025

  • Although I have been notified that the contractor has taken appropriate action, as of today’s date 1/8/25 the problem is still there and has not been attended to. I look forward to receiving your response

    Postiwyd yn ddienw am 11:23, Gwen 1 Awst 2025

  • Thank you for your comments. Please accept our apologies, the works raised for this enquiry were not committed on the system and now have been issued to the contractor to be completed within an estimated time frame of 28 days.

    Postiwyd gan Bromley Council am 12:07, Llun 18 Awst 2025

  • Appropriate action has been taken to resolve the issue.

    Cyflwr wedi newid i: Fixed

    Postiwyd gan Bromley Council am 15:25, Mer 20 Awst 2025

This report is now closed to updates from the public. Gallwch wneud adroddiad newydd am yr un lleoliad .