Wedi trwsio
Large and deep potholes all along lane from Ashmore to Leaves Green crescent.
Adroddwyd drwy desktop yn y categori Road Defect yn ddienw am 19:33, Llun 18 Mawrth 2024
Anfon at Bromley Council llai na munud yn hwyrach. Cyfeirnod FixMyStreet: 5733365.
There are too many to photograph but the worse are at Ashmore lane end and outside Rose Cottages. They are getting bigger and deeper making it a danger to our cars as getting impossible to miss. It has been like this for at least two months.
Diweddariadau
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
Cyflwr wedi newid i: In progress
Postiwyd gan Bromley Council
am 19:34, Llun 18 Mawrth 2024
-
We ask that multiple reports are logged separately so they can be forwarded to the appropriate contractor. Any necessary works can then be raised under the correct category and timescale. This also enables us to link works that are already raised.
Cyflwr wedi newid i: Ar gau
Postiwyd gan Bromley Council
am 16:56, Gwen 22 Mawrth 2024
-
To help us action and resolve this issue please could further information be provided as comments to this report. For example information such as a house number, a nearby junction or street light column ID, or a What3Words code can greatly help us to correctly identify the location while further details of the nature and scale of an issue (especially dumped rubbish) assists us co-ordinating an appropriate response.
Postiwyd gan Bromley Council
am 16:57, Gwen 22 Mawrth 2024
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
Cyflwr wedi newid i: In progress
Postiwyd gan Bromley Council
am 16:25, Iau 11 Ebrill 2024
-
The potholes in the lane between Ashmore Lane and Leaves Green Crescent still haven’t been filled. They are getting larger and deeper making them very difficult to avoid when driving.
Postiwyd yn ddienw am 21:09, Llun 15 Ebrill 2024
Yn parhau i fod ar agor, trwy holiadur -
Thank you for your updates and continued patience. A request is in the process of being raised for remedial works. However, I do not currently have a completion time frame.
Postiwyd gan Bromley Council
am 10:49, Maw 23 Ebrill 2024
-
We are continuing to investigate and working to resolve this report
Postiwyd gan Bromley Council
am 10:55, Maw 23 Ebrill 2024
-
Still not filled and getting worse.
Postiwyd yn ddienw am 22:10, Llun 13 Mai 2024
Yn parhau i fod ar agor, trwy holiadur -
Still not repaired
Postiwyd yn ddienw am 09:05, Maw 9 Gorffennaf 2024
Yn parhau i fod ar agor, trwy holiadur -
Still not fixed and the whole lane is getting worse.
Postiwyd yn ddienw am 13:10, Maw 6 Awst 2024
-
Still not fixed and the whole lane is getting worse.
Postiwyd yn ddienw am 18:28, Maw 6 Awst 2024
-
Still not fixed and the whole lane is getting worse.
Postiwyd yn ddienw am 17:54, Mer 7 Awst 2024
Yn parhau i fod ar agor, trwy holiadur -
A further request has been raised for further repair works, which will be carried out shortly.
Postiwyd gan Bromley Council
am 11:13, Maw 20 Awst 2024
-
Yn parhau i fod ar agor, trwy holiadur, 08:39, Gwen 6 Medi 2024
-
Can we an update please?
Postiwyd yn ddienw am 08:17, Iau 10 Hydref 2024
-
Appropriate action has been taken to resolve the issue.
Cyflwr wedi newid i: Fixed
Postiwyd gan Bromley Council
am 11:49, Iau 17 Hydref 2024
-
213 days to fix
Postiwyd yn ddienw am 13:11, Iau 17 Hydref 2024
This report is now closed to updates from the public. Gallwch wneud adroddiad newydd am yr un lleoliad .