Deep pot hole
Adroddwyd drwy iOS yn y categori Road Defect yn ddienw am 10:27, Llun 26 Chwefror 2024
Anfon at Bromley Council llai na munud yn hwyrach. Cyfeirnod FixMyStreet: 5631559.
Deep pot hole
Diweddariadau
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
Cyflwr wedi newid i: In progress
Postiwyd gan Bromley Council
am 10:27, Llun 26 Chwefror 2024
-
Our contractor has been notified to take the appropriate action.
Postiwyd gan Bromley Council
am 10:49, Llun 26 Chwefror 2024
-
In need of attention please
Postiwyd yn ddienw am 07:35, Maw 27 Chwefror 2024
-
Our contractor is arranging Traffic Management to allow them to carry out the work safely. Thank you for your patience.
Postiwyd gan Bromley Council
am 11:03, Mer 10 Ebrill 2024
-
Traffic Management has been arranged so that our contractor can carry out the work safely. Work is due to commence in May. Thank you for your patience.
Postiwyd gan Bromley Council
am 18:22, Maw 30 Ebrill 2024
-
First reported 65 days ago?
Postiwyd yn ddienw am 16:51, Mer 1 Mai 2024
-
Our contractor is aware of these repairs outstanding. The potholes have been made safe as a temporary measure but unfortunately Traffic Management is required to carry out the work safely and at present our Traffic department are working on a scheme near Foxgrove Road and only one Traffic Management scheme is allowed at one time.
Postiwyd gan Bromley Council
am 12:50, Maw 4 Mehefin 2024
-
First reported 99 days ago
Postiwyd yn ddienw am 16:19, Maw 4 Mehefin 2024
-
I'm sorry I cannot give an further updates. Our contractor is aware of these repairs that require Traffic Management but as reported above our Traffic department are carrying out works in the area and added repairs would cause major disruption.
Postiwyd gan Bromley Council
am 17:27, Iau 13 Mehefin 2024
-
Thanks, much appreciated.
Postiwyd yn ddienw am 18:06, Iau 13 Mehefin 2024
-
Unfortunately I cannot provide a start date whilst a Traffic scheme is in progress in Southend Road. Our contractor is aware that this work is outstanding. The area has been made safe. Thank you for your patience.
Postiwyd gan Bromley Council
am 12:15, Iau 18 Gorffennaf 2024
-
Our contractor is arranging Traffic Management and bus diversions at present. Work should commence shortly. Thank you for your patience.
Postiwyd gan Bromley Council
am 10:21, Iau 15 Awst 2024
-
First reported 171 days ago
Postiwyd yn ddienw am 13:09, Iau 15 Awst 2024
-
For information, the order for this repair remains outstanding within our contractor's planned schedule of work. Further arrangements are currently being undertaken to provide traffic management and/or the necessary specialist equipment in order to undertake these works.
Postiwyd gan Bromley Council
am 11:11, Mer 11 Medi 2024
-
Appropriate action has been taken to resolve the issue.
Cyflwr wedi newid i: Fixed
Postiwyd gan Bromley Council
am 04:56, Maw 24 Medi 2024
This report is now closed to updates from the public. Gallwch wneud adroddiad newydd am yr un lleoliad .