Adroddwyd drwy desktop yn y categori Road Defect yn ddienw am 09:37, Maw 13 Chwefror 2024 using FixMyStreet Pro

Anfon at Bromley Council llai na munud yn hwyrach. Cyfeirnod FixMyStreet: 5569848.

3 large potholes downhill just before jct for Durrant. Please fix QUICKLY before they get larger!

Diweddariadau

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    Cyflwr wedi newid i: In progress

    Postiwyd gan Bromley Council am 09:37, Maw 13 Chwefror 2024

  • In need of attention please

    Postiwyd yn ddienw am 07:41, Mer 14 Chwefror 2024

  • Further works are necessary to resolve the issue and have been scheduled for action.

    Postiwyd gan Bromley Council am 12:14, Mer 14 Chwefror 2024

  • Our contractor has been notified to take the appropriate action.

    Postiwyd gan Bromley Council am 21:42, Mer 14 Chwefror 2024

  • The contractor has attended site and made safe areas that were highlighted. This road is regularly inspected and any other defects that reach intervention level will be repaired accordingly.

    Postiwyd gan Bromley Council am 12:23, Gwen 19 Ebrill 2024

  • Regularly inspected, just like Shire Lane then!!!!!

    Postiwyd gan TfL am 15:42, Gwen 19 Ebrill 2024

  • Works at this location have been scheduled to the contractor to be completed as soon as practicable.

    Postiwyd gan Bromley Council am 17:17, Llun 20 Mai 2024

  • As soon as possible not good enough. WHEN?

    Postiwyd yn ddienw am 18:04, Llun 20 Mai 2024

  • Further works are necessary to resolve the issue and have been scheduled for action.

    Postiwyd gan Bromley Council am 12:54, Maw 4 Mehefin 2024

  • First reported 112 days ago

    Postiwyd yn ddienw am 19:22, Maw 4 Mehefin 2024

  • Thank you for your update.

    Thank you for using Fix My Street.

    Postiwyd gan Bromley Council am 14:41, Maw 11 Mehefin 2024

  • The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.

    Please continue to bear with us. We anticipate an early resolution to this report from this point in time.

    Postiwyd gan Bromley Council am 14:42, Maw 11 Mehefin 2024

  • Our contractor has been notified to take the appropriate action.

    Postiwyd gan Bromley Council am 14:44, Maw 11 Mehefin 2024

  • First reported 119 days ago

    Postiwyd yn ddienw am 18:34, Maw 11 Mehefin 2024

  • Thank you for your update.

    Thank you for using Fix My Street.

    Postiwyd gan Bromley Council am 12:31, Iau 18 Gorffennaf 2024

  • First reported 161 days ago

    Postiwyd yn ddienw am 21:40, Maw 23 Gorffennaf 2024

  • Further works are necessary to resolve the issue and have been scheduled for action.

    Postiwyd gan Bromley Council am 07:58, Mer 31 Gorffennaf 2024

  • Yeah, outstanding since February!

    Postiwyd yn ddienw am 08:40, Mer 31 Gorffennaf 2024

  • Now 169 days since this was first reported

    Postiwyd yn ddienw am 13:05, Mer 31 Gorffennaf 2024

  • Appropriate action has been taken to resolve the issue.

    Cyflwr wedi newid i: Fixed

    Postiwyd gan Bromley Council am 15:30, Llun 9 Medi 2024

  • 209 days to finally fix