Wedi trwsio
Centerline potholes on curve
Adroddwyd drwy desktop yn y categori Road Defect yn ddienw am 17:33, Iau 8 Chwefror 2024 using FixMyStreet Pro
Anfon at Bromley Council llai na munud yn hwyrach. Cyfeirnod FixMyStreet: 5550330.
Still waiting for a fix, dangerous esp to 2 wheelers.
Diweddariadau
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
Cyflwr wedi newid i: In progress
Postiwyd gan Bromley Council
am 17:34, Iau 8 Chwefror 2024
-
In need of attention please
Postiwyd yn ddienw am 07:37, Gwen 9 Chwefror 2024
-
Our contractor has been notified to take the appropriate action.
Postiwyd gan Bromley Council
am 13:35, Maw 13 Chwefror 2024
-
The contractors have scheduled repairs which will commence asap.
Postiwyd gan Bromley Council
am 12:08, Gwen 19 Ebrill 2024
-
And what exactly does asap mean? ASAP next week, next month, next year? No wonder you lose track of repairs. More accurate timescale please, like by the end of the month would be useful, and ties your contractors to actually doing something, or because it's Shire Lane will you just leave it to deteriorate indefinitely? ASAP is just another fob off, isn't it!
Postiwyd gan TfL am 15:46, Gwen 19 Ebrill 2024
-
First reported 71 days ago, no updates since February 2024. Very disappointing indeed.
Postiwyd yn ddienw am 18:43, Gwen 19 Ebrill 2024
-
Contractors to complete works under traffic management measures as soon as practicable.
Postiwyd gan Bromley Council
am 11:48, Iau 9 Mai 2024
-
Not good enough. What is your timescale to sort out?. Reported first back in early Feb. Hardly confidence inspiring, is it?
Postiwyd yn ddienw am 13:11, Iau 9 Mai 2024
-
First reported 92 days ago
Postiwyd yn ddienw am 15:35, Gwen 10 Mai 2024
-
The contractors to commence works next week.
Postiwyd gan Bromley Council
am 17:09, Llun 20 Mai 2024
-
The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.
Please continue to bear with us. We anticipate an early resolution to this report from this point in time.
Postiwyd gan Bromley Council
am 10:09, Mer 3 Gorffennaf 2024
-
Why has this been outstanding since JANUARY!!!! Does anybody in the council run a diary or check up on what is outstanding? Dangerous for 7 months now, not very impressive, in fact looks like nobody is interested actually. Is this just another promise that will come to nothing and we will be chasing YET AGAIN at the end of July?
Postiwyd yn ddienw am 11:24, Mer 3 Gorffennaf 2024
-
Now 146 days old
Postiwyd yn ddienw am 18:37, Mer 3 Gorffennaf 2024
-
Thank you for your update.
Thank you for using Fix My Street.
Postiwyd gan Bromley Council
am 16:51, Gwen 9 Awst 2024
-
First reported 183 days ago
Postiwyd yn ddienw am 19:00, Gwen 9 Awst 2024
-
Further works are necessary to resolve the issue and have been scheduled for action.
Postiwyd gan Bromley Council
am 08:04, Mer 4 Medi 2024
-
WHEN? Outstanding almost a year!
Postiwyd yn ddienw am 09:20, Mer 4 Medi 2024
-
First reported 209 days ago
Postiwyd yn ddienw am 11:33, Mer 4 Medi 2024
-
Appropriate action has been taken to resolve the issue.
Cyflwr wedi newid i: Fixed
Postiwyd gan Bromley Council
am 16:16, Llun 9 Medi 2024
-
214 days to fix.
Postiwyd yn ddienw am 18:53, Llun 9 Medi 2024
-
Further works are necessary to resolve the issue and have been scheduled for action.
Cyflwr wedi newid i: In progress
Postiwyd gan Bromley Council
am 05:32, Gwen 27 Medi 2024
-
Appropriate action has been taken to resolve the issue.
Cyflwr wedi newid i: Fixed
Postiwyd gan Bromley Council
am 08:35, Gwen 27 Medi 2024
This report is now closed to updates from the public. Gallwch wneud adroddiad newydd am yr un lleoliad .