Recent remedial repairs (following damage by HGVs during the new school build), are of a poor low-quality standard. Some of the replacement curb stones are a different size, some are cracked/chipped, and some have not been reset/replaced at all. There are gaps between the ‘new’ curbs and the road surface, which will allow water to ingress, which when frozen will expand and create further problems. The ‘tarmac’ coating on the path has already started to erode in some places at curb level. It seems that Edgebury estate is treated as some sort of appendage, and that ‘we’ will put up with shoddy repairs. Why should we? We pay our council tax just like everyone else in the Borough. I don’t know who signed these works off, but I suggest that if it were their own property they would not have done so; indeed, if the Leader of the Council lived in Slades Drive, it would be a different story. With the above in mind, may I request that a ‘revisit’ be made, with a view to surveying the whole of the pathway, from the junction with Edgehill Rd to the Slades Drive cul-de-sac. The attached photos do not give a full picture. I have others if you would like them.
Diweddariadau
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
Cyflwr wedi newid i: In progress
Postiwyd gan Bromley Council am 13:06, Mer 25 Hydref 2023
-
Our contractor has been notified to take the appropriate action.
Postiwyd gan Bromley Council am 14:12, Mer 25 Hydref 2023
-
The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.
Please continue to bear with us. We anticipate an early resolution to this report from this point in time.
Postiwyd gan Bromley Council am 12:16, Gwen 8 Rhagfyr 2023
-
Appropriate action has been taken to resolve the issue.
Cyflwr wedi newid i: Fixed
Postiwyd gan Bromley Council am 12:18, Gwen 8 Rhagfyr 2023
-
The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.
Please continue to bear with us. We anticipate an early resolution to this report from this point in time.
Cyflwr wedi newid i: In progress
Postiwyd gan Bromley Council am 13:43, Iau 28 Rhagfyr 2023
-
Our contractor has been notified to take the appropriate action.
Postiwyd gan Bromley Council am 10:40, Dydd Gwener 19 Ionawr 2024
-
The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.
Please continue to bear with us. We anticipate an early resolution to this report from this point in time.
Postiwyd gan Bromley Council am 11:22, Dydd Iau 22 Chwefror 2024
-
The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.
Please continue to bear with us. We anticipate an early resolution to this report from this point in time.
Postiwyd gan Bromley Council am 14:04, Dydd Iau 4 Ebrill 2024
-
The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.
Please continue to bear with us. We anticipate an early resolution to this report from this point in time.
Postiwyd gan Bromley Council am 07:34, Dydd Gwener 24 Mai 2024
-
The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.
Please continue to bear with us. We anticipate an early resolution to this report from this point in time
Postiwyd gan Bromley Council am 12:55, Dydd Iau 11 Gorffennaf 2024
-
The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.
Please continue to bear with us. We anticipate an early resolution to this report from this point in time.
Postiwyd gan Bromley Council am 08:54, Dydd Mercher 14 Awst 2024
-
Appropriate action has been taken to resolve the issue.
Cyflwr wedi newid i: Fixed
Postiwyd gan Bromley Council am 10:49, Dydd Mawrth 24 Medi 2024