Adroddwyd drwy desktop yn y categori Tree Requires Pruning yn ddienw am 09:48, Iau 19 Hydref 2023 using FixMyStreet Pro
Anfon at Bromley Council llai na munud yn hwyrach. Cyfeirnod FixMyStreet: 5112742.
Residents called as large tree is on her front street branches fell off someone came round to see and advised the tree would need taking down, residents on the street concerned as tree is still there and is dangerous. need looking at as contractor advised it was also dead.
Diweddariadau
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
Cyflwr wedi newid i: In progress
Postiwyd gan Bromley Council am 09:49, Iau 19 Hydref 2023
-
Our contractor has been notified to take the appropriate action.
Postiwyd gan Bromley Council am 15:42, Iau 19 Hydref 2023
-
Resident called to chase removal of the tree, resident is worried with the current winds, please can this be looked into
Postiwyd yn ddienw am 14:46, Llun 30 Hydref 2023
-
Our contractor has been notified to take appropriate action. We appreciate your patience on this matter.
Postiwyd gan Bromley Council am 17:21, Iau 2 Tachwedd 2023
-
Thank you for your patience whilst we work to resolve your issue.
Postiwyd gan Bromley Council am 11:23, Llun 18 Rhagfyr 2023
-
My apologies, the storm clearance process from three recent storms is causing delays to the completion of the works. The contractor will visit site as soon as possible to remove the tree. Thank you for your patience.
Postiwyd gan Bromley Council am 11:21, Dydd Llun 5 Chwefror 2024
-
Resident has called back as is worried that the tree is still in need of attention, they are worried that the tree will cause damage to there property, would this be able to be looked at as soon as possible. A vey large branch has fallen off the tree so resident is worried about it.
Postiwyd yn ddienw am 12:17, Dydd Mawrth 13 Chwefror 2024
-
My apologies for the delays in the completion of the works. The contractor has been chased up and requested that the works are undertaken as a priority.
Postiwyd gan Bromley Council am 16:06, Dydd Mercher 28 Chwefror 2024
-
Appropriate action has been taken to resolve the issue.
Cyflwr wedi newid i: Fixed
Postiwyd gan Bromley Council am 08:42, Dydd Sadwrn 30 Mawrth 2024
This report is now closed to updates from the public. Gallwch wneud adroddiad newydd am yr un lleoliad .